The kind of job we don't bid anymore


The kind of job we don't bid anymore

The Steel Erector's Playbook

Issue No. 04

A bid invite hit my inbox last week. Multi-story mid-rise. Downtown Chicago. Decent tonnage. Mid-tier developer.

I passed in ten minutes.

Three years ago I would have spent two days on that takeoff and gone in aggressive to win it. Now I preview the plans, run it against our criteria, and pass in ten minutes.

Here's what changed.

We sat down and studied our completed projects. The winners. The losers. The ones that paid and the ones that bled.

A pattern jumped out fast.

The multi-story buildings inside city limits were the worst performers in our portfolio. Tight logistics. No laydown. Tough union red tape. Heavy pedestrian and vehicle traffic killing our crane picks. Every one of those jobs ate hours we didn't price for.

The wins were a different animal entirely. Suburban industrial. Schools on summer breaks. Open lots with crane access. Single-fabricator coordination. The pattern was so clear it almost embarrassed me — I'd been chasing the wrong work for years.

That's when we built the scorecard.

The Bid Scorecard is a free filter I built so erectors can run this exact analysis on every bid in under ten minutes. It tells you where a job really stands before you commit a single estimating hour.

We score every bid 1 to 5 across 10 criteria — total out of 50. For that Chicago mid-rise, here's where it died:

Location and logistics risk. Union territory risk. Margin potential. Project complexity for our crew makeup. Schedule feasibility. Every one bottomed out.

The total didn't crack 20. The math confirmed what my gut already knew.

Now here's the part most owners get wrong about the number.

A low score doesn't always mean walk. It means pass or premium.

If the relationship's there — a GC or fabricator who's paid us right for years — we'll still bid a low-scoring job. But we build the risk into the price. We don't sharpen the pencil and hope. We charge for the exposure the scorecard is showing us.

What you never do is bid a weak job at a thin number and pray it works out. Hope is not a system. The score is telling you something — your job is to listen to it. Either you walk, or you make the risk pay.

And here's the other half most owners miss:

They score the bid after they've already spent ten hours on it. By then they're emotionally invested. They've talked to the GC. They've started planning the schedule. They want to win it.

You can't make a clean call once you're already in.

Score every bid in the first ten minutes — before you commit a single estimating hour. That's the whole point of filtering early: your best estimating effort goes to the jobs that actually fit your operation.

Your sweet spot is hiding in your last 20 completed jobs. Pull the records. Compare estimated hours to actual hours. Look at margin by project type, by GC, by location. The pattern is there. You just have to be honest enough to see it.

That's what made the difference for us.

— Dino

P.S. — Next week: the foreman daily report that protects you in court. Cheapest legal insurance in the business and almost nobody uses it.

One field-tested system per week to protect profit, reduce chaos, and build a business that runs without you.

DinoDePasquale.com

© The Steel Erector's Playbook. All rights reserved.

Dino Depasquale

Join The Steel Erector's Playbook — a weekly newsletter on bidding, contracts, cash flow, and the systems that separate struggling contractors from thriving companies. Subscribe and get the Steel Erector's Bid Scorecard free.

Read more from Dino Depasquale

The half-gone clutch on the hill What my dad taught me at a stop sign at 15 — and the one thing the trade can't teach you. The Steel Erector's Playbook Issue #5 The half-gone clutch on the hill I was 15. No license. Saturday. My dad had brought me to work with him, and on the way home we pulled up to a stop sign in his beat-up work truck — the one with the clutch already half gone. He stopped the truck, looked at me, and said, “Okay. You're going to drive this home.” I'd never driven stick in...

The Steel Erector's Playbook — Issue #3 THE STEEL ERECTOR'S PLAYBOOK Issue #3 We showed up with four truckloads of steel and nowhere to put it School project. 650 tons of structural steel total — including 100-foot-plus long-span joists for the gymnasium. Nice sized project. Our first mobilization was the north half — outer classrooms and hallway steel. Four truckloads. Five-man crew. Crane and operator on site. Everything scheduled, everything planned. Then we pulled in. The bricklayer had...

The Steel Erector's Playbook — Issue #2 Issue No. 02 The Steel Erector's Playbook Field-tested systems for steel erection owners The Confession I was guessing my labor rate for 15 years. I'll tell you something most owners won't. For most of my career, our hourly billing rate was an educated guess. We'd look at what we charged the previous year. Bump it up a few bucks. Check what we thought the market was doing. Talk to a couple of other guys. Settle on a number that felt right. That was the...